Define the hold points: what must be resolved before closing, finishing and decorating.
Before a surface is closed
Ask the project lead which investigations, trade work, required inspections and approvals must be complete before board is installed. The answer depends on the actual project; this planning sequence is not a permit or construction specification.
- Resolve the reason for any opening, damage or moisture issue.
- Identify existing-material assessment requirements before disturbance.
- Coordinate the work and checks for items that will be concealed.
- Confirm the board or assembly specified for each area with the responsible professional.
- Record who authorises the next stage.
Choose the decorative outcome early
Keep the finish schedule with the drywall brief: which surfaces remain visible, which receive texture, and which have a demanding paint or lighting condition. Include window and light locations in the conversation before finishing begins.
If cabinetry, trim or built-in furniture will change the visible surface, show the relevant drawings and ask the trades to agree their boundaries. A detail that exists only in someone’s head is easy to miss.
Use a sequence with decisions, not a fixed countdown
| Stage | Decision before progressing |
|---|---|
| Assess & define | The cause, existing materials, design and written scope are understood. |
| Coordinate & check | Concealed work and any required checks are complete before closing. |
| Board & finish | Installation and finishing follow the specified products and agreed finish. |
| Review & decorate | The responsible trades agree the surface and coating handover. |
| Complete & protect | Touch-ups, cleaning, remaining trade work and final protection are resolved. |
USG explains that cold or humid jobsite conditions can delay joint-compound drying. Agree who maintains the selected products’ required conditions between visits and who confirms readiness for the next coat or decoration. A booked painting date does not establish that compound is dry.
Source: USG
Give the handover a named owner
Identify who checks the surface before decoration, who supplies primer and paint, and how later damage is addressed. When several contractors are involved, a short written handover is clearer than assuming the next person will deal with it.
- Which rooms or surfaces are ready for the next trade?
- What remains incomplete or excluded?
- Who accepts the handover and records any touch-ups?
- What protection must remain until the renovation is complete?
Use the issued permit package to build the sequence
Burnaby places responsibility for necessary inspections on the permit holder and says the inspection list varies by permit. Have that person map the relevant release points into the renovation schedule. This is more useful than assuming a standard sequence or a guaranteed next-day visit will suit a restoration and a layout alteration equally.
Source: City of Burnaby
- Identify the owner of each inspection request and the person who reads the result.
- Leave time to resolve deficiencies without closing the area prematurely.
- Confirm the handover from assessed repair to boarding, finishing and decoration separately.
A few practical questions.
Should flooring be installed before drywall?
Agree the order with the project lead and the trades, considering access, protection, product requirements and what is already installed. There is no single sequence that fits every renovation.
When should I choose paint?
Share the intended colour, sheen and lighting while the drywall scope is being developed. A late decorative change may require the finish expectation to be reviewed.
Sources & editorial context
- Finishing Gypsum Panels in Cold, Humid, or Critical Light ConditionsUSG · Checked October 24, 2026
- Building InspectionsCity of Burnaby · Checked October 24, 2026
Technical references support the points linked above. The checklists and planning questions are editorial guidance, not a specification or an account of a contractor’s completed work.